| Description |
The Federal Emergency Management Agency required
significant infrastructure modifications at
the Mount weather Headquarters Complex in order
to upgrade physical security capabilities in
times of national emergency. This classified
complex becomes the hub of response activity
for everything from natural disasters to those
instigated by terrorist activities. Requiring
significant transportation requirements including
relocating over 1 mile of State Roads, reconfiguring
the entire entrance facility and security screening
point for the facility, all vehicular access,
and all associated utilities Shirley Contracting
Company LLC and their design build team was
requested to take on the project under an incredibly
aggressive schedule.
The Shirley Team completed over $ 4.9 million
of actual work in place coordinating with VDOT,
other State agencies, two local counties and
their agencies, FEMA, and other Federal Government
agencies. The work was begun in the late summer
of 2003 with the State Route 601 reloaction
completed by November 2003 and the balance of
the project completed by July 2004. Typically
under the normal process the design and construction
of a road complex of this type takes nearly
2 years including all permitting. The Route
601 design started in July of 2003 and the road
was opened to traffic in less than 4 months.
|