| |
|
|
 |
| |
 |
|
Incentives Help Accelerate Virginia
'Mixing Bowl' Work
Engineering News Record, May 14, 2001
by Aileen Cho
TWO MAJOR PHASES OF THE MASSIVE $585 million rehabilitation
of Interstate 95 south of Washington, D.C., are moving
nearly a year ahead of schedule. If all stays on track,
the Virginia Department of Transportation and Shirley
Contracting Corp. anticipate completing the work in
mid-August. That could net the contractor $10 million,
an amount the state says would be the largest early-completion
bonus in its history.
Jon Harman, contract manager for Lorton, Va. Based Shirley,
says the firm would receive $10 million if it completes
the work on its combined $90-million contract by Aug.
18. The work, begun in spring 1999, is contractually
set for completion in July 2002. Shirley would receive
a $5-million bonus if it completes the work by Nov.
17.
The overall eight-year project, known as the Mixing
Bowl, includes building 50 bridges, widening I-95 to
up to 24 lanes and rebuilding loops and off-ramps for
high occupancy vehicles near the town of Springfield.
VDOT wanted the second and third phases done quickly
to get a jump on the rest of the phases, and to minimize
traffic impact on downtown Springfield, says Steve Titunik,
an agency spokesman.
Shirley is replacing five old bridges with 15 new ones,
including four flyovers on the I-95 connection with
Route 644. The contract also includes work on 4 miles
of downtown Springfield's arterial roads and 35,000
sq m of mechanically stabilized walls. Also included
is moving 350,000 cu m of soil, laying 10,000 m of pipe
and paving the bridges while maintaining rush hour lanes
for 400,000 daily vehicles. Logistics of traffic management
and site access where a huge challenge, Harman says.
Last November, Shirley also won the contract for the
fourth phase, a $117-million A+B contract. Shirley plans
to utilize jack-and-bore methods in conjunction with
microtunneling for nearly 11,000 m of utilities. Excavation
of some 220,000 cu m will provide the roadway base for
the Capital Beltway outer loop and bridge approaches.
That project is slated for completion in 2003.
Titunik says VDOT may consider bonus incentives for
future contracts. The fifth-phase contract is already
out to bid with an award expected by July for extending
eastbound lanes of the Beltway crossing I-395 and for
widening loops on the west side of the I-95/395/495
interchange.
Phases "six and seven might go out as one contract,
which would be pretty hefty," Titunik says. "There might
be some partnering." Those phases will involve $100
million in widening the inner and outer loops of the
Beltway.
|
 |